Tracking 38,817 interconnection queue requests from 1996 to 2025
[Live Data] Updated from public data sources today. (What is the interconnection queue?)
Created by Steven Zhang & Chris Talley
Use the sidebar to filter.
See data table & graphs here.
Sign up for updates here.Created by Steven Zhang & Chris Talley
Queue changes in the last 1 week (see all)
Shooter 12kV
— 1MW battery + gas 🔋🔥 project in Orange, CA (CAISO). Proposed completion changed from March 15, 2020 to March 1, 2020
Vernon Repowering
— hydro 💧 project in Windham County, VT (ISO-NE). Proposed completion changed from March 13, 2008
Duda 12kV
— 0MW battery 🔋 project in Riverside, CA (CAISO). Proposed completion changed from August 1, 2018 to May 1, 2018
Harmony 12 kV Circuit, near structure 764247E, out of Bliss 66/12 kV Substation
— 5MW battery + solar 🔋☀️ project in Tulare, CA (CAISO). Proposed completion changed from October 1, 2024 to April 15, 2024
Arboles 16kV
— 0MW battery 🔋 project in Los Angeles, CA (CAISO). Proposed completion changed from March 31, 2017 to March 1, 2017
Goldtown 66/12kV Substation connected to the Boxcar 12 kV circuit
— 3MW solar ☀️ project in Kern, CA (CAISO). Proposed completion changed from July 7, 2017 to December 1, 2016
Colonia 66kV
— 70MW battery 🔋 project in Ventura, CA (CAISO). Proposed completion changed to February 1, 2021
Strinestown Solar Project
— 79MW solar ☀️ project in York County, PA (PJM). Proposed completion changed from December 31, 2024 to January 7, 2027
Lockhart 33 kV
— 4MW battery + solar 🔋☀️ project in San Bernardino, CA (CAISO). Proposed completion changed from December 1, 2023 to October 15, 2019
Roadway 12kV
— 2MW battery 🔋 project in San Bernardino, CA (CAISO). Proposed completion changed to June 7, 2024
ANDRETTI 12KV
— 0MW solar ☀️ project in San Bernardino, CA (CAISO). Proposed completion changed from May 31, 2011 to December 1, 2012
Antelope-Lancaster-Oasis 66 kV line
— 21MW solar ☀️ project in Los Angeles, CA (CAISO). Proposed completion changed from December 31, 2023 to December 31, 2022
Braves [test]
— 2MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed to October 1, 2018
Yarborough 12 kV
— 4MW battery + solar 🔋☀️ project in San Bernardino, CA (CAISO). Proposed completion changed to September 1, 2024
TBD
— 0MW battery 🔋 project in Kern, CA (CAISO). Proposed completion changed from June 15, 2015 to February 1, 2015
See Map in App
— 3MW solar ☀️ project in Kern, CA (CAISO). Proposed completion changed to September 1, 2016
The Distribution Provider’s new 3-way gas switch position 2 on the Distribution Provider’s Yorktown 12 kV distribution line out of Narrows 66/12 kV Substation
— 0MW battery 🔋 project in Los Angeles, CA (CAISO). Proposed completion changed from November 10, 2023 to April 9, 2023
Estero: Remac 16 kV Line
— 13MW gas 🔥 project in Ventura, CA (CAISO). Proposed completion changed from August 10, 2013 to December 31, 2011
Millinocket Frequency Conversion
— hydro 💧 project in Penobscot County, ME (ISO-NE). Proposed completion changed from June 15, 2019
ONTO–WEJN 138kV Line
— 42MW battery + solar 🔋☀️ project in Malheur, OR (Idaho Power Company). Proposed completion changed from June 1, 2022 to December 31, 2024
Circuit LAV11 out of Lava substation
— 0MW hydro 💧 project in Bannock, ID (PacifiCorp). Proposed completion changed from May 1, 2020 to January 22, 2021
Hudson 12kV
— 0MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed to December 1, 2015
Chris 12 kV line out of Watson 66/12 kV Substation
— 10MW battery 🔋 project in Los Angeles, CA (CAISO). Proposed completion changed from November 30, 2016 to October 31, 2016
Goleta 66kV Substation
— 102MW gas 🔥 project in Santa Barbara, CA (CAISO). Proposed completion changed to May 1, 2009
Regal 12kV
— 0MW solar ☀️ project in Los Angeles, CA (CAISO). Proposed completion changed to December 1, 2011
33/115 kV Casa Diablo Substation at the 33 kV bus.
— 44MW geothermal 🌋 project in Mono, CA (CAISO). Proposed completion changed from February 1, 2020 to September 1, 2011
Chrysler 16kV
— 0MW solar ☀️ project in Los Angeles, CA (CAISO). Proposed completion changed from September 30, 2024 to July 15, 2023
Wintersburg 12 kV Line
— 0MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed from July 31, 2015 to July 1, 2015
Dealer 12 kV distribution line out of Phelan 115/12 kV Substation.
— 3MW battery + solar 🔋☀️ project in Los Angeles, CA (CAISO). Proposed completion changed from December 1, 2023 to January 4, 2022
Vestal Substation 66 kV bus
— 88MW battery 🔋 project in Kern, CA (CAISO). Proposed completion changed from November 1, 2023 to March 15, 2022
Francis 66 kV Substation at the 66 kV bus.
— 42MW battery 🔋 project in Los Angeles, CA (CAISO). Proposed completion changed from April 30, 2025 to October 30, 2022
Cambridge 12kV
— 0MW battery 🔋 project in Riverside, CA (CAISO). Proposed completion changed from March 15, 2018 to October 1, 2017
A tap on the Distribution Provider’s Buckhorn 16 kV distribution line out of Fillmore 66/16 kV Substation
— 2MW solar ☀️ project in Ventura, CA (CAISO). Proposed completion changed from October 1, 2018 to June 30, 2018
Pecos 12kV
— 0MW solar ☀️ project in Los Angeles, CA (CAISO). Proposed completion changed from July 10, 2018 to October 1, 2017
Holgate Substation
— 20MW project in Kern, CA (CAISO). Proposed completion changed to December 31, 2013
Clark Junction Substation
— 19MW wind 💨 project in Clark County, SD (NorthWestern Energy). Proposed completion changed to December 2, 2012
Terminal substation distribution circuit
— 3MW biogas 🌿 project in Salt Lake, UT (PacifiCorp). Proposed completion changed from December 15, 2005 to July 20, 2006
Ladder 12 kV
— 1MW solar ☀️ project in San Bernardino, CA (CAISO). Proposed completion changed from August 1, 2025 to July 15, 2023
Westbrook Power
— gas 🔥 project in Cumberland County, ME (ISO-NE). Proposed completion changed from April 13, 2001
34.893038, -117.149175
— 10MW battery + solar 🔋☀️ project in San Bernardino, CA (CAISO). Proposed completion changed to May 31, 2025
Dogbane 12 kV Circuit
— 5MW battery 🔋 project in Kern, CA (CAISO). Proposed completion changed from February 1, 2026 to March 1, 2024
DESERT CENTER 12KV
— 1MW solar ☀️ project in Riverside, CA (CAISO). Proposed completion changed from July 27, 2014 to December 31, 2012
Grazide 12kV
— 0MW battery 🔋 project in Los Angeles, CA (CAISO). Proposed completion changed from June 25, 2018 to May 28, 2018
34.891979, -116.886963
— 10MW battery + solar 🔋☀️ project in San Bernardino, CA (CAISO). Proposed completion changed to May 31, 2025
Mccloud 16 kV
— 0MW battery 🔋 project in Los Angeles, CA (CAISO). Proposed completion changed from December 30, 2016 to October 28, 2016
Northfield Mt Upgrade #3
— 25MW pumped storage 💧 project in Franklin County, MA (ISO-NE). Proposed completion changed from June 17, 2011
Circuit PAN12 out of Panguitch substation
— 1MW battery 🔋 project in Garfield, UT (PacifiCorp). Proposed completion changed from May 31, 2018 to January 16, 2020
Kramer 115/33 kV
— 7MW battery + solar 🔋☀️ project in San Bernardino, CA (CAISO). Proposed completion changed to June 23, 2024
Mosquito 12 kV distribution line out of Kimball 66/12 kV Substation
— 4MW battery + gas + solar 🔋🔥☀️ project in San Bernardino, CA (CAISO). Proposed completion changed from December 6, 2019 to May 2, 2018
Riverside Substation, Great Falls, MT
— 3MW solar ☀️ project in Cascade County, MT (NorthWestern Energy). Proposed completion changed to July 31, 2016
Socrates 12kV
— 0MW battery 🔋 project in Los Angeles, CA (CAISO). Proposed completion changed from August 27, 2018 to May 28, 2018
Highgrove Substation 115 kV switchrack
— 260MW battery 🔋 project in Riverside, CA (CAISO). Proposed completion changed from December 31, 2023 to March 31, 2023
Circuit ENV12 out of Enterprise Valley substation
— 3MW solar ☀️ project in Iron, UT (PacifiCorp). Proposed completion changed from July 1, 2015 to September 30, 2015
Pellet 12kV
— 0MW battery 🔋 project in Los Angeles, CA (CAISO). Proposed completion changed from August 14, 2020 to March 30, 2020
Seabrook PSS Enabling
— nuclear ☢️ project in Rockingham County, NH (ISO-NE). Proposed completion changed from November 1, 2009
Alamogordo-Dona Ana 115kV Line
— 150MW battery + solar 🔋☀️ project in Otero County, NM (Tri-State Generation and Transmission Association). Proposed completion changed to June 28, 2024
Empresa 12kV
— 0MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed from January 15, 2018 to December 4, 2017
Litchfield substation - NG Western MA Area Cluster Study
— 9MW solar ☀️ project in Worcester County, MA (ISO-NE). Proposed completion changed from April 30, 2021
Augusta E. Side 115 kV SS - Augusta Area Study
— 4MW solar ☀️ project in Kennebec County, ME (ISO-NE). Proposed completion changed from March 25, 2022
STANDING ROCK 12KV
— 1MW solar ☀️ project in San Bernardino, CA (CAISO). Proposed completion changed from June 1, 2013 to October 1, 2010
Queensland 12kV
— 3MW solar ☀️ project in Los Angeles, CA (CAISO). Proposed completion changed from October 30, 2012 to October 30, 2015
Grandview substation
— 100MW battery + solar 🔋☀️ project in Benton, WA (PacifiCorp). Proposed completion changed from December 31, 2023 to December 17, 2026
Huntington Power Plant, Huntington, Utah
— 17MW coal 🏭 project in Emery, UT (PacifiCorp). Proposed completion changed from December 26, 2015 to May 2, 2012
Doble 33kV
— 1MW solar ☀️ project in San Bernardino, CA (CAISO). Proposed completion changed to March 4, 2019
Otay Mesa Substation - Distribution Circuit 150
— 1MW gas 🔥 project in San Diego, CA (CAISO). Proposed completion changed from April 1, 2013 to June 18, 2013
Rand 12 kV Line
— 0MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed from April 2, 2018 to December 1, 2015
Muirlands 12kV
— 0MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed to November 13, 2019
Midway-Union Gap transmission line
— 150MW battery + solar 🔋☀️ project in Yakima, WA (PacifiCorp). Proposed completion changed from October 1, 2025 to November 7, 2025
LENA 12KV
— 1MW solar ☀️ project in San Bernardino, CA (CAISO). Proposed completion changed from November 1, 2013 to June 30, 2011
Manchester Street Station Exciter Upgrades & incre
— 12MW gas 🔥 project in Providence County, RI (ISO-NE). Proposed completion changed from June 14, 2011
Marriott 12kV
— 0MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed from August 30, 2017 to January 1, 2018
138kV
— 18MW wind 💨 project in Twin Falls, ID (Idaho Power Company). Proposed completion changed from December 31, 2005 to February 16, 2009
230kV
— 20MW wind 💨 project in Elmore County, ID (Idaho Power Company). Proposed completion changed from June 30, 2011 to May 31, 2012
Sturgeon 12kV circuit
— 5MW solar ☀️ project in Tulare, CA (CAISO). Proposed completion changed to September 1, 2024
Tap 5D52 out of Madras substation
— 10MW solar ☀️ project in Jefferson, OR (PacifiCorp). Proposed completion changed from December 31, 2016 to May 25, 2018
Salem Harbor Unit 3 Exciter Replacement
— coal 🏭 project in Essex County, MA (ISO-NE). Proposed completion changed from May 4, 2007
Bryant Circuit, La Fresa 66/16 Sub
— 0MW battery 🔋 project in Los Angeles, CA (CAISO). Proposed completion changed from May 15, 2016 to March 1, 2016
Conning 12kV
— 1MW solar ☀️ project in Riverside, CA (CAISO). Proposed completion changed to June 30, 2011
Armijo 12 kV Circuit
— 5MW solar ☀️ project in San Bernardino, CA (CAISO). Proposed completion changed to April 1, 2025
Harmony 12kV circuit
— 5MW solar ☀️ project in Tulare, CA (CAISO). Proposed completion changed to September 1, 2024
Lamar 230kV Substation
— 398MW battery + solar 🔋☀️ project in Prowers County, CO (Tri-State Generation and Transmission Association). Proposed completion changed to May 1, 2029
Pisces 12kV
— 0MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed to February 15, 2018
Waterside Power
— gas 🔥 project in Fairfield County, CT (ISO-NE). Proposed completion changed from June 1, 2003
Circuit 5L49 out of Lakeport substation
— 1MW geothermal 🌋 project in Klamath, OR (PacifiCorp). Proposed completion changed from November 1, 2012 to March 14, 2014
A tap on the Distribution Provider’s Milk 12 kV distribution line out of Tulare 66/12 kV Substation
— 3MW solar ☀️ project in Tulare, CA (CAISO). Proposed completion changed from June 19, 2019 to July 1, 2017
Reed Point Substation, Reed Point
— 2MW solar ☀️ project in Stillwater County, MT (NorthWestern Energy). Proposed completion changed to April 1, 2016
Radnor 12kV Circuit
— 10MW battery + solar 🔋☀️ project in Tulare, CA (CAISO). Proposed completion changed to September 1, 2024
Emery substation
— 200MW battery + solar 🔋☀️ project in Emery, UT (PacifiCorp). Proposed completion changed from December 31, 2018 to August 31, 2024
NE Corner of Amboy Road and Hillcrest Road
— 1MW solar ☀️ project in San Bernardino, CA (CAISO). Proposed completion changed to May 1, 2011
Bragdon 12 kV
— 2MW solar ☀️ project in San Bernardino, CA (CAISO). Proposed completion changed to July 2, 2026
QUTZ–WJDY 138kV Substation
— 30MW battery + solar 🔋☀️ project in Grant, OR (Idaho Power Company). Proposed completion changed from November 30, 2021 to December 31, 2024
Darby 4.16kV
— 0MW battery 🔋 project in Los Angeles, CA (CAISO). Proposed completion changed from February 15, 2018 to October 19, 2017
Existing System on Line 40 from White City to Vilas Road
— 30MW biomass 🌿 project in Jackson, OR (PacifiCorp). Proposed completion changed from September 10, 2007 to February 3, 2009
Cos Cob Redevelopment
— oil ⛽ project in Fairfield County, CT (ISO-NE). Proposed completion changed from May 31, 2008
Aeolus substation
— 250MW wind 💨 project in Carbon, WY (PacifiCorp). Proposed completion changed from November 1, 2018 to November 1, 2020
138kV
— 40MW wind 💨 project in Twin Falls, ID (Idaho Power Company). Proposed completion changed from December 31, 2010 to November 15, 2012
Deacano 12 kV Line
— 0MW solar ☀️ project in San Bernardino, CA (CAISO). Proposed completion changed from August 31, 2013 to January 1, 2011
Terminal substation
— 199MW battery 🔋 project in Salt Lake, UT (PacifiCorp). Proposed completion changed from July 1, 2024 to February 6, 2031
Hinkle substation
— 1MW wind 💨 project in Umatilla, OR (PacifiCorp). Proposed completion changed from December 15, 2007 to January 11, 2010
Crystal Lake Substation - NG Western MA Area Cluster Study
— 24MW solar ☀️ project in Worcester County, MA (ISO-NE). Proposed completion changed from December 31, 2020
Wallingford GT Uprate
— gas 🔥 project in New Haven County, CT (ISO-NE). Proposed completion changed from May 31, 2022
Factor 16kV
— 0MW battery + solar 🔋☀️ project in Los Angeles, CA (CAISO). Proposed completion changed to August 1, 2015
Trautwein 12kV
— 0MW oil ⛽ project in Riverside, CA (CAISO). Proposed completion changed to February 20, 2017
DORAN 12KV CIRCUIT
— 10MW battery + solar 🔋☀️ project in Tulare, CA (CAISO). Proposed completion changed to September 1, 2024
Lucerne 33/12 kV
— 6MW battery + solar 🔋☀️ project in San Bernardino, CA (CAISO). Proposed completion changed to January 3, 2026
Sellers 12kV
— 0MW oil ⛽ project in San Bernardino, CA (CAISO). Proposed completion changed to September 11, 2017
Comerford Unit #1
— -17MW hydro 💧 project in Grafton County, NH (ISO-NE). Proposed completion changed from November 30, 2009
Tanager 12kV
— 0MW battery + solar 🔋☀️ project in Kern, CA (CAISO). Proposed completion changed from September 23, 2019 to April 23, 2019
115kV line north of Highgrove Sub
— 49MW gas 🔥 project in San Bernardino, CA (CAISO). Proposed completion changed to June 1, 2005
230 KV T-Line
— project in Chelan, WA (Chelan County Public Utility District). Proposed completion changed from February 1, 2026 to February 1, 2027
Weeks 12 kV line out of Narod 66/12 kV Substation
— 10MW battery 🔋 project in San Bernardino, CA (CAISO). Proposed completion changed from November 30, 2016 to October 31, 2016
RISEP Increase
— 66MW gas 🔥 project in Providence County, RI (ISO-NE). Proposed completion changed from November 12, 2012
Devers - Banning - Windpark 115 kV Line
— 40MW battery 🔋 project in Riverside, CA (CAISO). Proposed completion changed to April 1, 2020
Tripp Junction Substation
— 130MW wind 💨 project in Bon Homme County, SD (NorthWestern Energy). Proposed completion changed to June 15, 2014
The Distribution Provider’s 3-way switch on the Distribution Provider’s Cribbage 12kV distribution line out of Johanna 66/12kv Substation
— 10MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed from November 15, 2019 to December 1, 2018
Calmen 12kV
— 1MW solar ☀️ project in San Bernardino, CA (CAISO). Proposed completion changed to December 1, 2011
Craig-Meeker 345kV Line
— 145MW solar ☀️ project in Moffat County, CO (Tri-State Generation and Transmission Association). Proposed completion changed to June 30, 2024
Curtis 12 kV
— 15MW battery + solar 🔋☀️ project in Kern, CA (CAISO). Proposed completion changed to September 1, 2024
TIMCO 12KV
— 3MW solar ☀️ project in San Bernardino, CA (CAISO). Proposed completion changed from March 2, 2015 to December 15, 2011
Bingham Wind CNR Only
— wind 💨 project in Somerset County, ME (ISO-NE). Proposed completion changed from December 13, 2016
Canyon View Rd and Desert View Rd, Apple Valley CA 92308
— 1MW solar ☀️ project in San Bernardino, CA (CAISO). Proposed completion changed from December 31, 2012 to December 31, 2011
Wellgen Substation 66 KV bus
— 8MW battery 🔋 project in Tulare, CA (CAISO). Proposed completion changed from December 1, 2016 to November 1, 2016
Q3 new switching station near Cordova 230kV Substation
— 250MW battery + solar 🔋☀️ project in Sacramento County, CA (Sacramento Municipal Utility District). Proposed completion changed from December 31, 2027 to December 31, 2028
Krypton 12kV
— 0MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed from November 1, 2018 to August 27, 2018
Beijing 12 kV line
— 2MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed from June 30, 2018 to October 31, 2017
Dakota 12kV
— 0MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed from December 1, 2018 to August 1, 2018
Dinsmore Sub
— 50MW solar ☀️ project in Duval, FL (Jacksonville Electric Authority). Proposed completion changed from December 31, 2020 to December 31, 2026
Dixie 12kV
— 0MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed from January 21, 2019 to May 28, 2018
Rockair leg of Helijet - Little Rock - Palmdale - Rockair 66 kV line
— 50MW solar ☀️ project in Los Angeles, CA (CAISO). Proposed completion changed to March 1, 2011
Hinkle substation
— 10MW wind 💨 project in Umatilla, OR (PacifiCorp). Proposed completion changed from December 30, 2016 to December 18, 2020
Radnor 12 kV Line
— 0MW solar ☀️ project in Kern, CA (CAISO). Proposed completion changed from December 31, 2011 to December 31, 2012
N. Oxford Substation - NG Western MA Area Cluster Study
— 8MW solar ☀️ project in Worcester County, MA (ISO-NE). Proposed completion changed from December 30, 2020
13665 Felt Road Solar
— 1MW battery + solar 🔋☀️ project in Oxford County, ME (ISO-NE). Proposed completion changed from December 3, 2024
Oasis 66 kV Bus
— 20MW solar ☀️ project in Los Angeles, CA (CAISO). Proposed completion changed from October 13, 2015 to August 1, 2013
Dylan 115 kV Substation at the 115 kV bus
— 116MW battery 🔋 project in Riverside, CA (CAISO). Proposed completion changed from March 1, 2024 to October 15, 2021
Carodean 115/12 kV
— 10MW project in San Bernardino, CA (CAISO). Proposed completion changed to December 15, 2024
Milford Upgrades - Phase I
— 16MW gas 🔥 project in New Haven County, CT (ISO-NE). Proposed completion changed from June 5, 2017
El Nido: Seabass 16 kV line
— 0MW battery 🔋 project in Los Angeles, CA (CAISO). Proposed completion changed from September 25, 2014 to January 8, 2013
Storm 12kV
— 0MW solar ☀️ project in Los Angeles, CA (CAISO). Proposed completion changed to February 28, 2014
Victor-Black Mountain-Soport-Southcap-Southdown 115 kV line at Southdown Substation
— 20MW gas 🔥 project in San Bernardino, CA (CAISO). Proposed completion changed from April 1, 2022 to April 1, 2021
Midpoint–Humboldt 345kV Line
— 20MW solar ☀️ project in Twin Falls, ID (Idaho Power Company). Proposed completion changed from December 31, 2016 to December 1, 2022
Showcase 16kV
— 0MW battery 🔋 project in Los Angeles, CA (CAISO). Proposed completion changed from June 1, 2015 to December 20, 2015
Bluefield 12 kV
— 0MW solar ☀️ project in Orange, CA (CAISO). Proposed completion changed to July 15, 2023
Circuit WCD28 out of West Cedar substation
— 3MW solar ☀️ project in Iron, UT (PacifiCorp). Proposed completion changed from May 30, 2016 to December 13, 2016
Sanford Airport Solar CNR Only
— solar ☀️ project in York County, ME (ISO-NE). Proposed completion changed from August 2, 2023
LOFTUS 12KV
— 1MW solar ☀️ project in Los Angeles, CA (CAISO). Proposed completion changed from June 3, 2016 to March 1, 2011
Bahama 12kV
— 0MW solar ☀️ project in Orange, CA (CAISO). Proposed completion changed to September 12, 2018
Riverview Substation
— 2MW hydro 💧 project in Cascade County, MT (NorthWestern Energy). Proposed completion changed to April 2, 2021
Proctor Valley Substation - Distribution Circuit 591
— 3MW other storage 🔋 project in San Diego, CA (CAISO). Proposed completion changed from December 1, 2016 to February 6, 2018
Dressen 12 kV
— 3MW battery + solar 🔋☀️ project in San Bernardino, CA (CAISO). Proposed completion changed from July 1, 2025 to September 1, 2024
Stetson Wind II(Jimmey & Owl Mt.-UPC)
— 2MW wind 💨 project in Washington County, ME (ISO-NE). Proposed completion changed from March 12, 2010
Lighthipe Substation 66kV Bus
— 47MW gas 🔥 project in Los Angeles, CA (CAISO). Proposed completion changed to July 2, 2007
Huron 12kV
— 1MW solar ☀️ project in Los Angeles, CA (CAISO). Proposed completion changed to December 1, 2011
Bernice #22 circuit out of Bernice substation
— 0MW hydro 💧 project in Butte, ID (PacifiCorp). Proposed completion changed from October 15, 2008 to August 4, 2009
INDEPENDENCE-ISES - POWERLINE ROAD 500.0kV, Independence(A) (500kV) -Powerline(B) (500kV)
— 625MW solar ☀️ project in Jackson County, AR (MISO). Proposed completion changed from February 2, 2024 to July 20, 2029
Manchester Street Station increase
— gas 🔥 project in Providence County, RI (ISO-NE). Proposed completion changed from August 2, 2010
Twin Butte 12 kV
— 18MW battery + solar 🔋☀️ project in Tulare, CA (CAISO). Proposed completion changed to May 31, 2025
INDEPENDENCE-ISES - POWERLINE ROAD 500.0kV
— 652MW solar ☀️ project in Jackson County, AR (MISO). Proposed completion changed from February 2, 2024 to July 20, 2029
Rommel 12kV
— 0MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed to September 14, 2018
69kV line East of Bole Substation
— 10MW wind 💨 project in Teton County, MT (NorthWestern Energy). Proposed completion changed to May 1, 2012
Bardeen 12kV
— 1MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed from April 2, 2018 to January 1, 2018
Monsoon 12kV
— 0MW solar ☀️ project in Orange, CA (CAISO). Proposed completion changed from June 1, 2011 to June 11, 2011
Circuit 4L16, Langell Valley, out of Casebeer substation
— 4MW solar ☀️ project in Klamath, OR (PacifiCorp). Proposed completion changed from June 30, 2014 to December 14, 2018
Overall 12kV
— 3MW solar ☀️ project in Kern, CA (CAISO). Proposed completion changed to May 1, 2016
Northwest substation
— 25MW gas 🔥 project in Salt Lake, UT (PacifiCorp). Proposed completion changed from January 1, 2004 to October 6, 2004
Cottonwood-Savage 115 kV line near Cottonwood substation
— 200MW solar ☀️ project in San Bernardino, CA (CAISO). Proposed completion changed to January 1, 2010
Elliott Substation, 12kv Circuit 1266
— 10MW other storage 🔋 project in San Diego, CA (CAISO). Proposed completion changed from October 31, 2020 to October 18, 2023
Maplewood
— 0MW battery 🔋 project in Los Angeles, CA (CAISO). Proposed completion changed from January 31, 2017 to October 31, 2016
Ellis 66kV Substation
— 111MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed to June 30, 2021
Newhall - McBean 16kV
— 13MW battery 🔋 project in Los Angeles, CA (CAISO). Proposed completion changed to December 31, 2021
Styx PT 12kV
— 3MW project in San Bernardino, CA (CAISO). Proposed completion changed to November 1, 2022
Pellet 12kV
— 1MW battery + fuel cell 🔋🔋 project in Los Angeles, CA (CAISO). Proposed completion changed from November 16, 2018 to September 14, 2018
APN 3170-008-908, 34.660758N, -118.085094, 2000 Block E Avenue L, Lancaster CA 93535
— 3MW solar ☀️ project in Los Angeles, CA (CAISO). Proposed completion changed to November 1, 2016
Stitzer 12kV
— 0MW battery 🔋 project in Los Angeles, CA (CAISO). Proposed completion changed from December 1, 2018 to August 1, 2018
Budd 12 kV Circuit out of Pixley 66/12 kV Substation.
— 3MW solar ☀️ project in Tulare, CA (CAISO). Proposed completion changed from July 13, 2027 to June 3, 2026
Calli Valli 12kV Circuit, Little Rock 66/12kV substation
— 1MW solar ☀️ project in Los Angeles, CA (CAISO). Proposed completion changed from September 1, 2012 to September 1, 2011
Boone 12 kV
— 11MW solar ☀️ project in Kern, CA (CAISO). Proposed completion changed to September 1, 2024
Circuit RMD 12 out of Richmond substation
— 0MW hydro 💧 project in Cache, UT (PacifiCorp). Proposed completion changed from April 1, 2017 to May 1, 2017
Circuit PAN12 out of Panguitch substation
— 0MW solar ☀️ project in Garfield, UT (PacifiCorp). Proposed completion changed from May 31, 2018 to January 16, 2020
Circuit WCD28 out of West Cedar substation
— 3MW solar ☀️ project in Iron, UT (PacifiCorp). Proposed completion changed from May 30, 2016 to December 13, 2016
the new new 4-way gas swich position 3 on the Distribution Provider's Everest 12kV distribution line out of Mira Loma Substation
— 10MW battery 🔋 project in San Bernardino, CA (CAISO). Proposed completion changed from November 30, 2016 to October 31, 2016
RS II Solar substation
— 160MW battery 🔋 project in Sacramento County, CA (Sacramento Municipal Utility District). Proposed completion changed from December 1, 2027 to September 30, 2027
Raven substation
— 80MW solar ☀️ project in Sweetwater, WY (PacifiCorp). Proposed completion changed from November 1, 2018 to December 3, 2018
Paradise Substation, 12kv Circuit 320
— 10MW other storage 🔋 project in San Diego, CA (CAISO). Proposed completion changed from October 31, 2020 to November 22, 2023
Coolidge Solar
— 19MW solar ☀️ project in Windsor County, VT (ISO-NE). Proposed completion changed from December 20, 2018
Wilbur 12 kV
— 11MW battery + solar 🔋☀️ project in Tulare, CA (CAISO). Proposed completion changed to September 1, 2024
Georgia Mountain Community Wind
— 10MW wind 💨 project in Chittenden County, VT (ISO-NE). Proposed completion changed from December 31, 2012
Scarlet 12kV
— 2MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed from May 1, 2017 to April 1, 2017
Minneola 33/12 (D)
— 5MW solar ☀️ project in San Bernardino, CA (CAISO). Proposed completion changed to January 3, 2026
Heisman 12 kV Circuit
— 2MW solar ☀️ project in Los Angeles, CA (CAISO). Proposed completion changed from December 5, 2026 to October 3, 2026
Ave A and Sierra Hwy, North Antelope Valley, CA 93534
— 1MW solar ☀️ project in Los Angeles, CA (CAISO). Proposed completion changed to December 1, 2011
Viejo 66 kV bus
— 100MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed to March 31, 2019
SUN VILLAGE 12KV
— 1MW solar ☀️ project in Los Angeles, CA (CAISO). Proposed completion changed from July 1, 2013 to March 1, 2012
SUNNYVALE 12KV
— 1MW solar ☀️ project in San Bernardino, CA (CAISO). Proposed completion changed from April 30, 2013 to February 1, 2012
A tap on the Distribution Provider's Brittle Bush 12 kV Circuit out of Cal City 33/12 kV Substation
— 3MW solar ☀️ project in Kern, CA (CAISO). Proposed completion changed from March 15, 2016 to March 1, 2016
Merlin 16kV
— 0MW battery 🔋 project in Los Angeles, CA (CAISO). Proposed completion changed from July 16, 2018 to June 18, 2018
Lake Road Generating Unit 3
— gas + oil 🔥⛽ project in Windham County, CT (ISO-NE). Proposed completion changed from May 22, 2002
LOFTUS 12KV
— 1MW solar ☀️ project in Los Angeles, CA (CAISO). Proposed completion changed from December 5, 2014 to March 1, 2011
Alterra 12kV
— 1MW battery + solar 🔋☀️ project in San Bernardino, CA (CAISO). Proposed completion changed from June 15, 2018 to November 30, 2017
12 kV Butte Circuit
— 5MW project in Kern, CA (CAISO). Proposed completion changed to November 1, 2022
Shooter 12kV
— 1MW battery + gas 🔋🔥 project in Orange, CA (CAISO). Proposed completion changed from March 15, 2020 to March 1, 2020
Vernon Repowering
— hydro 💧 project in Windham County, VT (ISO-NE). Proposed completion changed from March 13, 2008
Duda 12kV
— 0MW battery 🔋 project in Riverside, CA (CAISO). Proposed completion changed from August 1, 2018 to May 1, 2018
Harmony 12 kV Circuit, near structure 764247E, out of Bliss 66/12 kV Substation
— 5MW battery + solar 🔋☀️ project in Tulare, CA (CAISO). Proposed completion changed from October 1, 2024 to April 15, 2024
Arboles 16kV
— 0MW battery 🔋 project in Los Angeles, CA (CAISO). Proposed completion changed from March 31, 2017 to March 1, 2017
Goldtown 66/12kV Substation connected to the Boxcar 12 kV circuit
— 3MW solar ☀️ project in Kern, CA (CAISO). Proposed completion changed from July 7, 2017 to December 1, 2016
Colonia 66kV
— 70MW battery 🔋 project in Ventura, CA (CAISO). Proposed completion changed to February 1, 2021
Strinestown Solar Project
— 79MW solar ☀️ project in York County, PA (PJM). Proposed completion changed from December 31, 2024 to January 7, 2027
Lockhart 33 kV
— 4MW battery + solar 🔋☀️ project in San Bernardino, CA (CAISO). Proposed completion changed from December 1, 2023 to October 15, 2019
Roadway 12kV
— 2MW battery 🔋 project in San Bernardino, CA (CAISO). Proposed completion changed to June 7, 2024
ANDRETTI 12KV
— 0MW solar ☀️ project in San Bernardino, CA (CAISO). Proposed completion changed from May 31, 2011 to December 1, 2012
Antelope-Lancaster-Oasis 66 kV line
— 21MW solar ☀️ project in Los Angeles, CA (CAISO). Proposed completion changed from December 31, 2023 to December 31, 2022
Braves [test]
— 2MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed to October 1, 2018
Yarborough 12 kV
— 4MW battery + solar 🔋☀️ project in San Bernardino, CA (CAISO). Proposed completion changed to September 1, 2024
TBD
— 0MW battery 🔋 project in Kern, CA (CAISO). Proposed completion changed from June 15, 2015 to February 1, 2015
See Map in App
— 3MW solar ☀️ project in Kern, CA (CAISO). Proposed completion changed to September 1, 2016
The Distribution Provider’s new 3-way gas switch position 2 on the Distribution Provider’s Yorktown 12 kV distribution line out of Narrows 66/12 kV Substation
— 0MW battery 🔋 project in Los Angeles, CA (CAISO). Proposed completion changed from November 10, 2023 to April 9, 2023
Estero: Remac 16 kV Line
— 13MW gas 🔥 project in Ventura, CA (CAISO). Proposed completion changed from August 10, 2013 to December 31, 2011
Millinocket Frequency Conversion
— hydro 💧 project in Penobscot County, ME (ISO-NE). Proposed completion changed from June 15, 2019
ONTO–WEJN 138kV Line
— 42MW battery + solar 🔋☀️ project in Malheur, OR (Idaho Power Company). Proposed completion changed from June 1, 2022 to December 31, 2024
Circuit LAV11 out of Lava substation
— 0MW hydro 💧 project in Bannock, ID (PacifiCorp). Proposed completion changed from May 1, 2020 to January 22, 2021
Hudson 12kV
— 0MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed to December 1, 2015
Chris 12 kV line out of Watson 66/12 kV Substation
— 10MW battery 🔋 project in Los Angeles, CA (CAISO). Proposed completion changed from November 30, 2016 to October 31, 2016
Goleta 66kV Substation
— 102MW gas 🔥 project in Santa Barbara, CA (CAISO). Proposed completion changed to May 1, 2009
Regal 12kV
— 0MW solar ☀️ project in Los Angeles, CA (CAISO). Proposed completion changed to December 1, 2011
33/115 kV Casa Diablo Substation at the 33 kV bus.
— 44MW geothermal 🌋 project in Mono, CA (CAISO). Proposed completion changed from February 1, 2020 to September 1, 2011
Chrysler 16kV
— 0MW solar ☀️ project in Los Angeles, CA (CAISO). Proposed completion changed from September 30, 2024 to July 15, 2023
Wintersburg 12 kV Line
— 0MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed from July 31, 2015 to July 1, 2015
Dealer 12 kV distribution line out of Phelan 115/12 kV Substation.
— 3MW battery + solar 🔋☀️ project in Los Angeles, CA (CAISO). Proposed completion changed from December 1, 2023 to January 4, 2022
Vestal Substation 66 kV bus
— 88MW battery 🔋 project in Kern, CA (CAISO). Proposed completion changed from November 1, 2023 to March 15, 2022
Francis 66 kV Substation at the 66 kV bus.
— 42MW battery 🔋 project in Los Angeles, CA (CAISO). Proposed completion changed from April 30, 2025 to October 30, 2022
Cambridge 12kV
— 0MW battery 🔋 project in Riverside, CA (CAISO). Proposed completion changed from March 15, 2018 to October 1, 2017
A tap on the Distribution Provider’s Buckhorn 16 kV distribution line out of Fillmore 66/16 kV Substation
— 2MW solar ☀️ project in Ventura, CA (CAISO). Proposed completion changed from October 1, 2018 to June 30, 2018
Pecos 12kV
— 0MW solar ☀️ project in Los Angeles, CA (CAISO). Proposed completion changed from July 10, 2018 to October 1, 2017
Holgate Substation
— 20MW project in Kern, CA (CAISO). Proposed completion changed to December 31, 2013
Clark Junction Substation
— 19MW wind 💨 project in Clark County, SD (NorthWestern Energy). Proposed completion changed to December 2, 2012
Terminal substation distribution circuit
— 3MW biogas 🌿 project in Salt Lake, UT (PacifiCorp). Proposed completion changed from December 15, 2005 to July 20, 2006
Ladder 12 kV
— 1MW solar ☀️ project in San Bernardino, CA (CAISO). Proposed completion changed from August 1, 2025 to July 15, 2023
Westbrook Power
— gas 🔥 project in Cumberland County, ME (ISO-NE). Proposed completion changed from April 13, 2001
34.893038, -117.149175
— 10MW battery + solar 🔋☀️ project in San Bernardino, CA (CAISO). Proposed completion changed to May 31, 2025
Dogbane 12 kV Circuit
— 5MW battery 🔋 project in Kern, CA (CAISO). Proposed completion changed from February 1, 2026 to March 1, 2024
DESERT CENTER 12KV
— 1MW solar ☀️ project in Riverside, CA (CAISO). Proposed completion changed from July 27, 2014 to December 31, 2012
Grazide 12kV
— 0MW battery 🔋 project in Los Angeles, CA (CAISO). Proposed completion changed from June 25, 2018 to May 28, 2018
34.891979, -116.886963
— 10MW battery + solar 🔋☀️ project in San Bernardino, CA (CAISO). Proposed completion changed to May 31, 2025
Mccloud 16 kV
— 0MW battery 🔋 project in Los Angeles, CA (CAISO). Proposed completion changed from December 30, 2016 to October 28, 2016
Northfield Mt Upgrade #3
— 25MW pumped storage 💧 project in Franklin County, MA (ISO-NE). Proposed completion changed from June 17, 2011
Circuit PAN12 out of Panguitch substation
— 1MW battery 🔋 project in Garfield, UT (PacifiCorp). Proposed completion changed from May 31, 2018 to January 16, 2020
Kramer 115/33 kV
— 7MW battery + solar 🔋☀️ project in San Bernardino, CA (CAISO). Proposed completion changed to June 23, 2024
Mosquito 12 kV distribution line out of Kimball 66/12 kV Substation
— 4MW battery + gas + solar 🔋🔥☀️ project in San Bernardino, CA (CAISO). Proposed completion changed from December 6, 2019 to May 2, 2018
Riverside Substation, Great Falls, MT
— 3MW solar ☀️ project in Cascade County, MT (NorthWestern Energy). Proposed completion changed to July 31, 2016
Socrates 12kV
— 0MW battery 🔋 project in Los Angeles, CA (CAISO). Proposed completion changed from August 27, 2018 to May 28, 2018
Highgrove Substation 115 kV switchrack
— 260MW battery 🔋 project in Riverside, CA (CAISO). Proposed completion changed from December 31, 2023 to March 31, 2023
Circuit ENV12 out of Enterprise Valley substation
— 3MW solar ☀️ project in Iron, UT (PacifiCorp). Proposed completion changed from July 1, 2015 to September 30, 2015
Pellet 12kV
— 0MW battery 🔋 project in Los Angeles, CA (CAISO). Proposed completion changed from August 14, 2020 to March 30, 2020
Seabrook PSS Enabling
— nuclear ☢️ project in Rockingham County, NH (ISO-NE). Proposed completion changed from November 1, 2009
Alamogordo-Dona Ana 115kV Line
— 150MW battery + solar 🔋☀️ project in Otero County, NM (Tri-State Generation and Transmission Association). Proposed completion changed to June 28, 2024
Empresa 12kV
— 0MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed from January 15, 2018 to December 4, 2017
Litchfield substation - NG Western MA Area Cluster Study
— 9MW solar ☀️ project in Worcester County, MA (ISO-NE). Proposed completion changed from April 30, 2021
Augusta E. Side 115 kV SS - Augusta Area Study
— 4MW solar ☀️ project in Kennebec County, ME (ISO-NE). Proposed completion changed from March 25, 2022
STANDING ROCK 12KV
— 1MW solar ☀️ project in San Bernardino, CA (CAISO). Proposed completion changed from June 1, 2013 to October 1, 2010
Queensland 12kV
— 3MW solar ☀️ project in Los Angeles, CA (CAISO). Proposed completion changed from October 30, 2012 to October 30, 2015
Grandview substation
— 100MW battery + solar 🔋☀️ project in Benton, WA (PacifiCorp). Proposed completion changed from December 31, 2023 to December 17, 2026
Huntington Power Plant, Huntington, Utah
— 17MW coal 🏭 project in Emery, UT (PacifiCorp). Proposed completion changed from December 26, 2015 to May 2, 2012
Doble 33kV
— 1MW solar ☀️ project in San Bernardino, CA (CAISO). Proposed completion changed to March 4, 2019
Otay Mesa Substation - Distribution Circuit 150
— 1MW gas 🔥 project in San Diego, CA (CAISO). Proposed completion changed from April 1, 2013 to June 18, 2013
Rand 12 kV Line
— 0MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed from April 2, 2018 to December 1, 2015
Muirlands 12kV
— 0MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed to November 13, 2019
Midway-Union Gap transmission line
— 150MW battery + solar 🔋☀️ project in Yakima, WA (PacifiCorp). Proposed completion changed from October 1, 2025 to November 7, 2025
LENA 12KV
— 1MW solar ☀️ project in San Bernardino, CA (CAISO). Proposed completion changed from November 1, 2013 to June 30, 2011
Manchester Street Station Exciter Upgrades & incre
— 12MW gas 🔥 project in Providence County, RI (ISO-NE). Proposed completion changed from June 14, 2011
Marriott 12kV
— 0MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed from August 30, 2017 to January 1, 2018
138kV
— 18MW wind 💨 project in Twin Falls, ID (Idaho Power Company). Proposed completion changed from December 31, 2005 to February 16, 2009
230kV
— 20MW wind 💨 project in Elmore County, ID (Idaho Power Company). Proposed completion changed from June 30, 2011 to May 31, 2012
Sturgeon 12kV circuit
— 5MW solar ☀️ project in Tulare, CA (CAISO). Proposed completion changed to September 1, 2024
Tap 5D52 out of Madras substation
— 10MW solar ☀️ project in Jefferson, OR (PacifiCorp). Proposed completion changed from December 31, 2016 to May 25, 2018
Salem Harbor Unit 3 Exciter Replacement
— coal 🏭 project in Essex County, MA (ISO-NE). Proposed completion changed from May 4, 2007
Bryant Circuit, La Fresa 66/16 Sub
— 0MW battery 🔋 project in Los Angeles, CA (CAISO). Proposed completion changed from May 15, 2016 to March 1, 2016
Conning 12kV
— 1MW solar ☀️ project in Riverside, CA (CAISO). Proposed completion changed to June 30, 2011
Armijo 12 kV Circuit
— 5MW solar ☀️ project in San Bernardino, CA (CAISO). Proposed completion changed to April 1, 2025
Harmony 12kV circuit
— 5MW solar ☀️ project in Tulare, CA (CAISO). Proposed completion changed to September 1, 2024
Lamar 230kV Substation
— 398MW battery + solar 🔋☀️ project in Prowers County, CO (Tri-State Generation and Transmission Association). Proposed completion changed to May 1, 2029
Pisces 12kV
— 0MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed to February 15, 2018
Waterside Power
— gas 🔥 project in Fairfield County, CT (ISO-NE). Proposed completion changed from June 1, 2003
Circuit 5L49 out of Lakeport substation
— 1MW geothermal 🌋 project in Klamath, OR (PacifiCorp). Proposed completion changed from November 1, 2012 to March 14, 2014
A tap on the Distribution Provider’s Milk 12 kV distribution line out of Tulare 66/12 kV Substation
— 3MW solar ☀️ project in Tulare, CA (CAISO). Proposed completion changed from June 19, 2019 to July 1, 2017
Reed Point Substation, Reed Point
— 2MW solar ☀️ project in Stillwater County, MT (NorthWestern Energy). Proposed completion changed to April 1, 2016
Radnor 12kV Circuit
— 10MW battery + solar 🔋☀️ project in Tulare, CA (CAISO). Proposed completion changed to September 1, 2024
Emery substation
— 200MW battery + solar 🔋☀️ project in Emery, UT (PacifiCorp). Proposed completion changed from December 31, 2018 to August 31, 2024
NE Corner of Amboy Road and Hillcrest Road
— 1MW solar ☀️ project in San Bernardino, CA (CAISO). Proposed completion changed to May 1, 2011
Bragdon 12 kV
— 2MW solar ☀️ project in San Bernardino, CA (CAISO). Proposed completion changed to July 2, 2026
QUTZ–WJDY 138kV Substation
— 30MW battery + solar 🔋☀️ project in Grant, OR (Idaho Power Company). Proposed completion changed from November 30, 2021 to December 31, 2024
Darby 4.16kV
— 0MW battery 🔋 project in Los Angeles, CA (CAISO). Proposed completion changed from February 15, 2018 to October 19, 2017
Existing System on Line 40 from White City to Vilas Road
— 30MW biomass 🌿 project in Jackson, OR (PacifiCorp). Proposed completion changed from September 10, 2007 to February 3, 2009
Cos Cob Redevelopment
— oil ⛽ project in Fairfield County, CT (ISO-NE). Proposed completion changed from May 31, 2008
Aeolus substation
— 250MW wind 💨 project in Carbon, WY (PacifiCorp). Proposed completion changed from November 1, 2018 to November 1, 2020
138kV
— 40MW wind 💨 project in Twin Falls, ID (Idaho Power Company). Proposed completion changed from December 31, 2010 to November 15, 2012
Deacano 12 kV Line
— 0MW solar ☀️ project in San Bernardino, CA (CAISO). Proposed completion changed from August 31, 2013 to January 1, 2011
Terminal substation
— 199MW battery 🔋 project in Salt Lake, UT (PacifiCorp). Proposed completion changed from July 1, 2024 to February 6, 2031
Hinkle substation
— 1MW wind 💨 project in Umatilla, OR (PacifiCorp). Proposed completion changed from December 15, 2007 to January 11, 2010
Crystal Lake Substation - NG Western MA Area Cluster Study
— 24MW solar ☀️ project in Worcester County, MA (ISO-NE). Proposed completion changed from December 31, 2020
Wallingford GT Uprate
— gas 🔥 project in New Haven County, CT (ISO-NE). Proposed completion changed from May 31, 2022
Factor 16kV
— 0MW battery + solar 🔋☀️ project in Los Angeles, CA (CAISO). Proposed completion changed to August 1, 2015
Trautwein 12kV
— 0MW oil ⛽ project in Riverside, CA (CAISO). Proposed completion changed to February 20, 2017
DORAN 12KV CIRCUIT
— 10MW battery + solar 🔋☀️ project in Tulare, CA (CAISO). Proposed completion changed to September 1, 2024
Lucerne 33/12 kV
— 6MW battery + solar 🔋☀️ project in San Bernardino, CA (CAISO). Proposed completion changed to January 3, 2026
Sellers 12kV
— 0MW oil ⛽ project in San Bernardino, CA (CAISO). Proposed completion changed to September 11, 2017
Comerford Unit #1
— -17MW hydro 💧 project in Grafton County, NH (ISO-NE). Proposed completion changed from November 30, 2009
Tanager 12kV
— 0MW battery + solar 🔋☀️ project in Kern, CA (CAISO). Proposed completion changed from September 23, 2019 to April 23, 2019
115kV line north of Highgrove Sub
— 49MW gas 🔥 project in San Bernardino, CA (CAISO). Proposed completion changed to June 1, 2005
230 KV T-Line
— project in Chelan, WA (Chelan County Public Utility District). Proposed completion changed from February 1, 2026 to February 1, 2027
Weeks 12 kV line out of Narod 66/12 kV Substation
— 10MW battery 🔋 project in San Bernardino, CA (CAISO). Proposed completion changed from November 30, 2016 to October 31, 2016
RISEP Increase
— 66MW gas 🔥 project in Providence County, RI (ISO-NE). Proposed completion changed from November 12, 2012
Devers - Banning - Windpark 115 kV Line
— 40MW battery 🔋 project in Riverside, CA (CAISO). Proposed completion changed to April 1, 2020
Tripp Junction Substation
— 130MW wind 💨 project in Bon Homme County, SD (NorthWestern Energy). Proposed completion changed to June 15, 2014
The Distribution Provider’s 3-way switch on the Distribution Provider’s Cribbage 12kV distribution line out of Johanna 66/12kv Substation
— 10MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed from November 15, 2019 to December 1, 2018
Calmen 12kV
— 1MW solar ☀️ project in San Bernardino, CA (CAISO). Proposed completion changed to December 1, 2011
Craig-Meeker 345kV Line
— 145MW solar ☀️ project in Moffat County, CO (Tri-State Generation and Transmission Association). Proposed completion changed to June 30, 2024
Curtis 12 kV
— 15MW battery + solar 🔋☀️ project in Kern, CA (CAISO). Proposed completion changed to September 1, 2024
TIMCO 12KV
— 3MW solar ☀️ project in San Bernardino, CA (CAISO). Proposed completion changed from March 2, 2015 to December 15, 2011
Bingham Wind CNR Only
— wind 💨 project in Somerset County, ME (ISO-NE). Proposed completion changed from December 13, 2016
Canyon View Rd and Desert View Rd, Apple Valley CA 92308
— 1MW solar ☀️ project in San Bernardino, CA (CAISO). Proposed completion changed from December 31, 2012 to December 31, 2011
Wellgen Substation 66 KV bus
— 8MW battery 🔋 project in Tulare, CA (CAISO). Proposed completion changed from December 1, 2016 to November 1, 2016
Q3 new switching station near Cordova 230kV Substation
— 250MW battery + solar 🔋☀️ project in Sacramento County, CA (Sacramento Municipal Utility District). Proposed completion changed from December 31, 2027 to December 31, 2028
Krypton 12kV
— 0MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed from November 1, 2018 to August 27, 2018
Beijing 12 kV line
— 2MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed from June 30, 2018 to October 31, 2017
Dakota 12kV
— 0MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed from December 1, 2018 to August 1, 2018
Dinsmore Sub
— 50MW solar ☀️ project in Duval, FL (Jacksonville Electric Authority). Proposed completion changed from December 31, 2020 to December 31, 2026
Dixie 12kV
— 0MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed from January 21, 2019 to May 28, 2018
Rockair leg of Helijet - Little Rock - Palmdale - Rockair 66 kV line
— 50MW solar ☀️ project in Los Angeles, CA (CAISO). Proposed completion changed to March 1, 2011
Hinkle substation
— 10MW wind 💨 project in Umatilla, OR (PacifiCorp). Proposed completion changed from December 30, 2016 to December 18, 2020
Radnor 12 kV Line
— 0MW solar ☀️ project in Kern, CA (CAISO). Proposed completion changed from December 31, 2011 to December 31, 2012
N. Oxford Substation - NG Western MA Area Cluster Study
— 8MW solar ☀️ project in Worcester County, MA (ISO-NE). Proposed completion changed from December 30, 2020
13665 Felt Road Solar
— 1MW battery + solar 🔋☀️ project in Oxford County, ME (ISO-NE). Proposed completion changed from December 3, 2024
Oasis 66 kV Bus
— 20MW solar ☀️ project in Los Angeles, CA (CAISO). Proposed completion changed from October 13, 2015 to August 1, 2013
Dylan 115 kV Substation at the 115 kV bus
— 116MW battery 🔋 project in Riverside, CA (CAISO). Proposed completion changed from March 1, 2024 to October 15, 2021
Carodean 115/12 kV
— 10MW project in San Bernardino, CA (CAISO). Proposed completion changed to December 15, 2024
Milford Upgrades - Phase I
— 16MW gas 🔥 project in New Haven County, CT (ISO-NE). Proposed completion changed from June 5, 2017
El Nido: Seabass 16 kV line
— 0MW battery 🔋 project in Los Angeles, CA (CAISO). Proposed completion changed from September 25, 2014 to January 8, 2013
Storm 12kV
— 0MW solar ☀️ project in Los Angeles, CA (CAISO). Proposed completion changed to February 28, 2014
Victor-Black Mountain-Soport-Southcap-Southdown 115 kV line at Southdown Substation
— 20MW gas 🔥 project in San Bernardino, CA (CAISO). Proposed completion changed from April 1, 2022 to April 1, 2021
Midpoint–Humboldt 345kV Line
— 20MW solar ☀️ project in Twin Falls, ID (Idaho Power Company). Proposed completion changed from December 31, 2016 to December 1, 2022
Showcase 16kV
— 0MW battery 🔋 project in Los Angeles, CA (CAISO). Proposed completion changed from June 1, 2015 to December 20, 2015
Bluefield 12 kV
— 0MW solar ☀️ project in Orange, CA (CAISO). Proposed completion changed to July 15, 2023
Circuit WCD28 out of West Cedar substation
— 3MW solar ☀️ project in Iron, UT (PacifiCorp). Proposed completion changed from May 30, 2016 to December 13, 2016
Sanford Airport Solar CNR Only
— solar ☀️ project in York County, ME (ISO-NE). Proposed completion changed from August 2, 2023
LOFTUS 12KV
— 1MW solar ☀️ project in Los Angeles, CA (CAISO). Proposed completion changed from June 3, 2016 to March 1, 2011
Bahama 12kV
— 0MW solar ☀️ project in Orange, CA (CAISO). Proposed completion changed to September 12, 2018
Riverview Substation
— 2MW hydro 💧 project in Cascade County, MT (NorthWestern Energy). Proposed completion changed to April 2, 2021
Proctor Valley Substation - Distribution Circuit 591
— 3MW other storage 🔋 project in San Diego, CA (CAISO). Proposed completion changed from December 1, 2016 to February 6, 2018
Dressen 12 kV
— 3MW battery + solar 🔋☀️ project in San Bernardino, CA (CAISO). Proposed completion changed from July 1, 2025 to September 1, 2024
Stetson Wind II(Jimmey & Owl Mt.-UPC)
— 2MW wind 💨 project in Washington County, ME (ISO-NE). Proposed completion changed from March 12, 2010
Lighthipe Substation 66kV Bus
— 47MW gas 🔥 project in Los Angeles, CA (CAISO). Proposed completion changed to July 2, 2007
Huron 12kV
— 1MW solar ☀️ project in Los Angeles, CA (CAISO). Proposed completion changed to December 1, 2011
Bernice #22 circuit out of Bernice substation
— 0MW hydro 💧 project in Butte, ID (PacifiCorp). Proposed completion changed from October 15, 2008 to August 4, 2009
INDEPENDENCE-ISES - POWERLINE ROAD 500.0kV, Independence(A) (500kV) -Powerline(B) (500kV)
— 625MW solar ☀️ project in Jackson County, AR (MISO). Proposed completion changed from February 2, 2024 to July 20, 2029
Manchester Street Station increase
— gas 🔥 project in Providence County, RI (ISO-NE). Proposed completion changed from August 2, 2010
Twin Butte 12 kV
— 18MW battery + solar 🔋☀️ project in Tulare, CA (CAISO). Proposed completion changed to May 31, 2025
INDEPENDENCE-ISES - POWERLINE ROAD 500.0kV
— 652MW solar ☀️ project in Jackson County, AR (MISO). Proposed completion changed from February 2, 2024 to July 20, 2029
Rommel 12kV
— 0MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed to September 14, 2018
69kV line East of Bole Substation
— 10MW wind 💨 project in Teton County, MT (NorthWestern Energy). Proposed completion changed to May 1, 2012
Bardeen 12kV
— 1MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed from April 2, 2018 to January 1, 2018
Monsoon 12kV
— 0MW solar ☀️ project in Orange, CA (CAISO). Proposed completion changed from June 1, 2011 to June 11, 2011
Circuit 4L16, Langell Valley, out of Casebeer substation
— 4MW solar ☀️ project in Klamath, OR (PacifiCorp). Proposed completion changed from June 30, 2014 to December 14, 2018
Overall 12kV
— 3MW solar ☀️ project in Kern, CA (CAISO). Proposed completion changed to May 1, 2016
Northwest substation
— 25MW gas 🔥 project in Salt Lake, UT (PacifiCorp). Proposed completion changed from January 1, 2004 to October 6, 2004
Cottonwood-Savage 115 kV line near Cottonwood substation
— 200MW solar ☀️ project in San Bernardino, CA (CAISO). Proposed completion changed to January 1, 2010
Elliott Substation, 12kv Circuit 1266
— 10MW other storage 🔋 project in San Diego, CA (CAISO). Proposed completion changed from October 31, 2020 to October 18, 2023
Maplewood
— 0MW battery 🔋 project in Los Angeles, CA (CAISO). Proposed completion changed from January 31, 2017 to October 31, 2016
Ellis 66kV Substation
— 111MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed to June 30, 2021
Newhall - McBean 16kV
— 13MW battery 🔋 project in Los Angeles, CA (CAISO). Proposed completion changed to December 31, 2021
Styx PT 12kV
— 3MW project in San Bernardino, CA (CAISO). Proposed completion changed to November 1, 2022
Pellet 12kV
— 1MW battery + fuel cell 🔋🔋 project in Los Angeles, CA (CAISO). Proposed completion changed from November 16, 2018 to September 14, 2018
APN 3170-008-908, 34.660758N, -118.085094, 2000 Block E Avenue L, Lancaster CA 93535
— 3MW solar ☀️ project in Los Angeles, CA (CAISO). Proposed completion changed to November 1, 2016
Stitzer 12kV
— 0MW battery 🔋 project in Los Angeles, CA (CAISO). Proposed completion changed from December 1, 2018 to August 1, 2018
Budd 12 kV Circuit out of Pixley 66/12 kV Substation.
— 3MW solar ☀️ project in Tulare, CA (CAISO). Proposed completion changed from July 13, 2027 to June 3, 2026
Calli Valli 12kV Circuit, Little Rock 66/12kV substation
— 1MW solar ☀️ project in Los Angeles, CA (CAISO). Proposed completion changed from September 1, 2012 to September 1, 2011
Boone 12 kV
— 11MW solar ☀️ project in Kern, CA (CAISO). Proposed completion changed to September 1, 2024
Circuit RMD 12 out of Richmond substation
— 0MW hydro 💧 project in Cache, UT (PacifiCorp). Proposed completion changed from April 1, 2017 to May 1, 2017
Circuit PAN12 out of Panguitch substation
— 0MW solar ☀️ project in Garfield, UT (PacifiCorp). Proposed completion changed from May 31, 2018 to January 16, 2020
Circuit WCD28 out of West Cedar substation
— 3MW solar ☀️ project in Iron, UT (PacifiCorp). Proposed completion changed from May 30, 2016 to December 13, 2016
the new new 4-way gas swich position 3 on the Distribution Provider's Everest 12kV distribution line out of Mira Loma Substation
— 10MW battery 🔋 project in San Bernardino, CA (CAISO). Proposed completion changed from November 30, 2016 to October 31, 2016
RS II Solar substation
— 160MW battery 🔋 project in Sacramento County, CA (Sacramento Municipal Utility District). Proposed completion changed from December 1, 2027 to September 30, 2027
Raven substation
— 80MW solar ☀️ project in Sweetwater, WY (PacifiCorp). Proposed completion changed from November 1, 2018 to December 3, 2018
Paradise Substation, 12kv Circuit 320
— 10MW other storage 🔋 project in San Diego, CA (CAISO). Proposed completion changed from October 31, 2020 to November 22, 2023
Coolidge Solar
— 19MW solar ☀️ project in Windsor County, VT (ISO-NE). Proposed completion changed from December 20, 2018
Wilbur 12 kV
— 11MW battery + solar 🔋☀️ project in Tulare, CA (CAISO). Proposed completion changed to September 1, 2024
Georgia Mountain Community Wind
— 10MW wind 💨 project in Chittenden County, VT (ISO-NE). Proposed completion changed from December 31, 2012
Scarlet 12kV
— 2MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed from May 1, 2017 to April 1, 2017
Minneola 33/12 (D)
— 5MW solar ☀️ project in San Bernardino, CA (CAISO). Proposed completion changed to January 3, 2026
Heisman 12 kV Circuit
— 2MW solar ☀️ project in Los Angeles, CA (CAISO). Proposed completion changed from December 5, 2026 to October 3, 2026
Ave A and Sierra Hwy, North Antelope Valley, CA 93534
— 1MW solar ☀️ project in Los Angeles, CA (CAISO). Proposed completion changed to December 1, 2011
Viejo 66 kV bus
— 100MW battery 🔋 project in Orange, CA (CAISO). Proposed completion changed to March 31, 2019
SUN VILLAGE 12KV
— 1MW solar ☀️ project in Los Angeles, CA (CAISO). Proposed completion changed from July 1, 2013 to March 1, 2012
SUNNYVALE 12KV
— 1MW solar ☀️ project in San Bernardino, CA (CAISO). Proposed completion changed from April 30, 2013 to February 1, 2012
A tap on the Distribution Provider's Brittle Bush 12 kV Circuit out of Cal City 33/12 kV Substation
— 3MW solar ☀️ project in Kern, CA (CAISO). Proposed completion changed from March 15, 2016 to March 1, 2016
Merlin 16kV
— 0MW battery 🔋 project in Los Angeles, CA (CAISO). Proposed completion changed from July 16, 2018 to June 18, 2018
Lake Road Generating Unit 3
— gas + oil 🔥⛽ project in Windham County, CT (ISO-NE). Proposed completion changed from May 22, 2002
LOFTUS 12KV
— 1MW solar ☀️ project in Los Angeles, CA (CAISO). Proposed completion changed from December 5, 2014 to March 1, 2011
Alterra 12kV
— 1MW battery + solar 🔋☀️ project in San Bernardino, CA (CAISO). Proposed completion changed from June 15, 2018 to November 30, 2017
12 kV Butte Circuit
— 5MW project in Kern, CA (CAISO). Proposed completion changed to November 1, 2022
U.S. county map of interconnection requests for 1998
- No. requests
- 106
- Total capacity
- 23.74 GW
For 1998
Data last updated Mar 29, 2025, 9:09 PM UTC
1998 interconnection capacity over time, all states, by date enqueued
- Total Interconnection Requests
- Total Capacity (MW)
- No. requests
- 106
- Total capacity
- 23.74 GW
For 1998
1998 interconnection requests & capacity by state
- Total Interconnection Requests
- Total Capacity (MW)
Current active in queue capacity by power market and generation type
Current active in queue capacity by power market and generation type

Data Table
Data last updated Mar 29, 2025, 9:09 PM UTC
(Click here to expand table to full screen)- No. requests
- 106
- Total capacity
- 23.74 GW
For 1998
FAQs
Q: Where is this data from?
A: This dataset has been built using publicly-available data from ISOs/RTOS and non-ISO utilities. We update this data at least once a day.
Q: What is an ISO, RTO, and/or non-ISO utility?
A: An Independent System Operator (ISO) or Regional Transmission Organization (RTO) is a non-profit organization that operates the high-voltage electric power transmission grid in a specific region, ensuring reliability and providing non-discriminatory access. ISOs and RTOs play a critical role in the electric power industry, helping to ensure that the grid is reliable and that electricity is delivered to consumers at a reasonable cost. Learn more about ISOs and RTOs here.A non-ISO utility is an electric utility that does not operate under the umbrella of an ISO or RTO. Non-ISO utilities are typically smaller utilities that operate in rural or remote areas, facing challenges such as meeting the same reliability standards as ISOs and RTOs, but without the same resources and economies of scale.
Q: What is an interconnection queue?
A: What is an interconnection queue?
An interconnection queue is a list of power generation and transmission projects that have requested to connect to the electric grid. The queue is managed by the grid operator, which is typically an independent system operator (ISO) or regional transmission organization (RTO).
Q: Why is the interconnection queue important?
A: The interconnection queue is important because it ensures that new power generation and transmission projects can be safely and reliably connected to the grid. The grid operator reviews each project to assess its impact on the grid and to make sure that it will not compromise the reliability of the electric system. To learn more about interconnection queues, see this NPR Planet Money episode"Green Energy Gridlock"and this article/podcast from Volts.
Q: Where can I contact the owners, submit feature requests, get data, or submit an error?
A: Please email us if you have any questions, see an error, want to request data, or have feature requests.
Q: Who are you?
A: 👋 This tool is brought to you by Chris Talley and Steven Zhang . We are long-time Silicon Valley software engineers who build tools to help people discover public structured and unstructured data. Check out our work here:
We also run a low-code/automation consultancy here: Deal Ops Automation — low-code & no-code consultancy.
- ClimateTechList - the web's most comprehensive climate tech jobs site (30,000+ jobs from 1,000 climate tech companies, updated daily
- WARN Tracker- Live Layoffs from Public WARN records
We also run a low-code/automation consultancy here: Deal Ops Automation — low-code & no-code consultancy.
Q: How can I access the underlying data?
A:
Interconnection.fyi
Tracking U.S. ISO & utility interconnection queues
Stay up to date via our email newsletter:
Interconnection requests in list format
All transmission grid interconnection requests All distribution grid (DG) interconnection requestsInsights
Charts State of interconnection queues — January 2024All blog postsOther energy & climate tools
Inflation Reduction Act Bill Text Viewer ToolClimate Tech Jobs Tracker (30,000+ jobs)Climate Tech Hiring Trends & ChartsRequests by power market
Requests by status
Interconnection queue requests by state
Interconnection queue requests by generation transmission owner
Alberta Electric System OperatorAllegheny PowerAlliant Energy EastAlliant Energy WestAmeren IllinoisAmeren MissouriAmerican Electric PowerAmerican Municipal PowerAmerican Transmission CompanyAmerican Transmission SystemsArizona Public ServiceArkansas Electric Cooperative CorporationAssociated Electric CooperativeAvista UtilitiesBaltimore Gas and ElectricBangor Hydro ElectricBasin Electric Power CooperativeBig Rivers Electric CorporationBlack Hills Cheyenne Light Fuel and Power TransmissionBlack Hills Colorado ElectricBlack Hills PowerBonneville Power AdministrationCedar Falls UtilitiesCentral Hudson Gas and ElectricCentral Maine PowerCentral Power Electric CooperativeChelan County Public Utility DistrictCity Utilities of Springfield MissouriCity Water, Light and PowerCity of Columbia, MissouriCity of Muscatine, IowaCleco HoldingsColorado River Storage Project TransmissionColorado Springs UtilitiesCommonwealth EdisonConsolidated EdisonConsumers EnergyCooperative EnergyCorn Belt Power CooperativeDCR TransmissionDairyland Power CooperativeDayton Power and LightDelmarva Power and LightDesertLinkDominion EnergyDominion Energy South CarolinaDuke EnergyDuke Energy CarolinasDuke Energy FloridaDuke Energy IndianaDuke Energy Ohio and KentuckyDuke Energy ProgressDuquesne Light CompanyEast Kentucky Power CooperativeEast River Electric Power CooperativeEast Texas Electric CooperativeEl Paso ElectricEmpire District Electric CompanyEntergyEntergy ArkansasEntergy LouisianaEntergy MississippiEntergy New OrleansEntergy TexasEssential PowerEvergyEvergy Missouri WestEversourceEwington Energy SystemsFirstEnergyFlorida Power and LightGeorgia TransmissionGrand River Dam AuthorityGrand River EnergyGrant County Public Utility DistrictGridLianceGridLiance WestGridUnityHenderson Municipal Power and LightHoosier EnergyHorizon West TransmissionISO New EnglandITC Great PlainsITC MidwestITC TransmissionIdaho Power CompanyImperial Irrigation DistrictIndependence Power and LightIndianapolis Power and LightJacksonville Electric AuthorityJersey Central Power and LightKACYKansas City Board of Public UtilitiesKansas City Power and LightKansas Power PoolLS PowerLS Power Grid New YorkLafayette Utilities SystemLea County Electric Cooperative
Lincoln Electric SystemLong Island Power AuthorityLos Angeles Department of Water and PowerLouisville Gas and Electric and Kentucky Utilities EnergyLoveland Area Projects TransmissionLower Yellowstone Rural Electric CooperativeMadison Gas and ElectricMaine Public ServiceManitoba HydroMetropolitan Edison CompanyMichigan Electric Transmission CompanyMichigan Public Power AgencyMid-Kansas Electric CompanyMidAmerican EnergyMidcontinent Independent System OperatorMidwest EnergyMinnesota PowerMinnkota Power CooperativeMissouri River Energy ServicesMissouri Western Energy CorporationMontana-Dakota UtilitiesMunicipal Commission of BoonvilleNAEANV EnergyNational GridNavajo-CrystalNebraska Public Power DistrictNew York Power AuthorityNew York State Electric and GasNew York TranscoNextEra Energy TransmissionNorthWestern EnergyNortheast UtilitiesNorthern Indiana Public ServiceNorthern States Power CompanyNorthwest Iowa Power CooperativeNorthwestern Wisconsin Electric CompanyOhio Valley Electric CorporationOklahoma Gas and ElectricOld Dominion Electric CooperativeOmaha Public Power DistrictOrange and RocklandOrlando Utilities CommissionOtter Tail Power CompanyPECO Energy CompanyPJMPPL CorporationPacifiCorpPacific Gas and Electric CompanyPennsylvania Electric CompanyPlatte River Power AuthorityPortland General ElectricPotomac Electric Power CompanyPrairie PowerPublic Service Company Of ColoradoPublic Service Company of New MexicoPublic Service Electric and GasPuget Sound EnergyRochester Gas and ElectricRochester Public UtilitiesRockland Electric CompanySacramento Municipal Utility DistrictSalt River ProjectSan Diego Gas and ElectricSantee CooperSeminole Electric CooperativeSouth Mississippi Electric Power AssociationSouthern California EdisonSouthern CompanySouthern Illinois Power CooperativeSouthern Indiana Gas and Electric CompanySouthern Maryland Electric CooperativeSouthern Minnesota Municipal Power AgencySouthwestern Power AdministrationSouthwestern Public Service CompanySunflower Electric Power CorporationTacoma Public UtilitiesTampa Electric CompanyTennessee Valley AuthorityTransource MissouriTri-State Generation and Transmission AssociationTucson Electric PowerUnited Gas Improvement CompanyUnited Illuminating CompanyUpper Peninsula Power CompanyValley Electric AssociationVillage of ArcadeWAPA Sierra NevadaWAPA/BEPC/HCPD Integrated SystemWabash Valley Power AssociationWestar EnergyWestern Area Power AdministrationWestern Area Power Administration Desert Southwest RegionWestern Farmers Electric CooperativeWisconsin Electric Power CompanyWisconsin Public Service CorporationWolverine Power Supply CooperativeXcel Energy
Interconnection requests by year
Requests in 2025Requests in 2024Requests in 2023Requests in 2022Requests in 2021Requests in 2020Requests in 2019Requests in 2018Requests in 2017Requests in 2016Requests in 2015Requests in 2014Requests in 2013Requests in 2012Requests in 2011Requests in 2010Requests in 2009Requests in 2008Requests in 2007Requests in 2006Requests in 2005Requests in 2004Requests in 2003Requests in 2002Requests in 2001Requests in 2000Requests in 1999Requests in 1998Requests in 1997Requests in 1996Requests in 1989© 2025 Interconnection.fyi. All rights reserved.